The short answer
- Commercial and industrial buildings: almost always need full planning permission.
- Farm buildings on 5 hectares or more: many can use agricultural permitted development, after notifying the council.
- Stables and riding arenas for leisure: usually need full planning permission.
- A garage or workshop in your garden: can be permitted development if it is low enough. Many steel garages are too tall.
- Building Regulations: a separate approval, needed for almost every new building.
This is general guidance for England, not legal advice. Rules change and every site is different. Check with your local planning authority or on the Planning Portal before you commit.
Planning and Building Regulations are different things
Planning permission is about whether a building should be there at all: its use, size, appearance and effect on neighbours and the landscape. Your local planning authority decides it.
Building Regulations are about whether the building is safe and efficient: its structure, fire safety and energy use. Building control signs it off.
Commercial and industrial buildings
A new commercial building almost always needs full planning permission. Because a steel building is made to order, details such as height, door positions, cladding colour and landscaping can be adjusted before the application goes in.
There is one useful exception. Some extensions to existing industrial and warehouse buildings can be permitted development under Class H of Part 7 of the General Permitted Development Order, within limits on size, height and distance from the boundary. Sites in protected areas have tighter limits.
Farm buildings
On agricultural units of 5 hectares or more, many new farm buildings can be built under agricultural permitted development (Class A of Part 6). Since May 2024 a new building can cover up to 1,500 m² of ground, up from 1,000 m².
There are also limits on height and distance from roads and houses, and buildings for livestock near homes have extra restrictions.
Permitted development does not mean you can just build. You must notify the council first, and they can ask for prior approval of the siting, design and external appearance. Allow 28 days for that.
Smaller holdings, buildings over the limits, and buildings that are not reasonably necessary for agriculture need full planning permission.
Stables and riding arenas
Keeping horses for leisure is not agriculture in planning terms. Stables and arenas usually need full planning permission, and outdoor lighting is often the sticking point.
A garage or workshop at home
An outbuilding in the garden of a house can be permitted development if it is for use with the house, single storey, and within these limits:
- eaves no higher than 2.5 m;
- overall height no more than 4 m with a dual-pitched roof, or 3 m with any other roof;
- no more than 2.5 m high overall if it is within 2 m of a boundary;
- not in front of the house;
- outbuildings and extensions together covering no more than half the land around the original house.
Many steel garages and workshops have eaves above 2.5 m to take a tall door, so they need planning permission. Running a business from the building, flats, listed buildings and homes in National Parks and National Landscapes have tighter rules.
Canopies and carports
Canopies on commercial sites usually need planning permission. Since December 2023, solar canopies over existing non-domestic car parks can be permitted development within limits, including on height and distance from homes. Ask your council before you rely on it.
Protected landscapes and Green Belt
Where your site is matters as much as what you build. National Parks and National Landscapes (formerly Areas of Outstanding Natural Beauty) expect buildings to fit the landscape. Dark, recessive colours, lower eaves and careful siting help.
Green Belt land only allows new buildings in limited cases. Flood zones need a flood risk assessment. Conservation areas and sites near listed buildings get extra scrutiny of design and materials.
In West Sussex, the South Downs National Park Authority decides applications inside the park. Building in West Sussex →
What goes into an application
- A site location plan and a block plan.
- Elevations and floor plans of the building, with materials and colours.
- A design and access statement, for some applications.
- Supporting reports where needed: flood risk, ecology, drainage, transport or noise.
The 3D designer produces scale drawings of your building that you can use to start the conversation with your planning officer.
How long it takes
Councils aim to decide most applications within 8 weeks, or 13 weeks for major developments, such as buildings over 1,000 m². Agricultural prior notifications have a 28-day period. Allow time before that to prepare drawings and reports. Fabrication cannot start until the design is fixed.
Building Regulations
The main parts that apply to steel buildings are Part A (structure), Part B (fire safety) and Part L (energy). Some agricultural buildings are exempt, but most commercial ones are not. For a commercial building, building control usually needs full plans.
Tips for a smoother application
- Talk to the planning officer early. Many councils offer pre-application advice.
- Choose colours that suit the setting. Anthracite, olive green and grey usually sit better in the countryside than bright white.
- Keep it as low as the use allows. Height is the thing neighbours and officers notice first.
- Fix the size before you apply. Changing it afterwards can mean a new application.