Is your site ready?

A short checklist for the day the steel arrives. Most delays on site come from access, ground or foundations, so check these early.

Getting the steel to you

  • Lorry route. Steel and cladding usually arrive on an articulated lorry, up to 16.5 m long. Check it can reach the site, turn and leave.
  • Gates, bridges and weight limits. Measure the narrowest gate and look for weight or width limits on the way in.
  • Overhead cables and trees. Cranes and lifts must stay well clear of overhead power lines. If lines cross the site or the access, tell us and speak to the network operator early.
  • Somewhere to unload. A firm, clear area beside the building to unload and lay out the steel and the panels.

The ground and the foundations

  • Firm, level working area. Cranes and scissor lifts need firm, level ground around and inside the building's footprint.
  • Pads built to the foundation plan. Each column stands on a concrete pad with holding-down bolts cast in.
  • Concrete cured. The pads must be strong enough to take the frame before erection starts.
  • Bolts checked. The position and level of every holding-down bolt is checked against the plan before the steel arrives. A bolt in the wrong place stops the job.
  • Buried services found. Drains, cables and pipes are located before anyone digs.

On the day

  • Water, power and welfare. A site needs toilets, washing and somewhere to shelter. These are a legal duty on construction sites.
  • Neighbours and working hours. Agree working hours, and tell neighbours about deliveries and crane days.
  • Other trades kept clear. Nobody works under or beside the frame while it is going up.
  • Weather. Steel erection stops in high wind, so allow some slack in the programme.

Who does what

On a kit, you or your contractor are responsible for all of this. On supply and erect, you provide the foundations and the access, and the erection crew does the lifting. On turnkey, we agree the whole list with you first. Whichever you choose, the law (CDM 2015) gives the client duties too, so ask us if you're unsure who is responsible for what.

General guidance for England. Your site survey confirms what your site needs. See also foundations and the rules we design to.